The time required to manufacture an elevator can vary significantly based on several factors, including the type of elevator, the complexity of the design, customization requirements, and the manufacturer's production capabilities. Here's a general overview of the timeline:
Design and Customization (2-6 weeks):
- Standard Elevators: For standard models with minimal customization, this phase might take about 2-4 weeks.
- Custom Elevators: For highly customized elevators, including bespoke designs and features, this phase can extend to 4-6 weeks or more, depending on the complexity.
Manufacturing (4-12 weeks):
- Standard Elevators: Manufacturing a standard elevator can typically take around 4-8 weeks.
- Custom Elevators: Manufacturing a custom rresidential elevator manufacturer elevator can take longer, often between 8-12 weeks, as it involves additional steps such as custom fabrication, special finishes, and bespoke components.
Quality Control and Testing (1-2 weeks):
- Once the elevator is manufactured, it undergoes rigorous quality control checks and testing to ensure all components function correctly and meet safety standards. This phase usually takes 1-2 weeks.
Shipping and Delivery (1-4 weeks):
- Shipping times can vary based on the destination. For local deliveries, it might take 1-2 weeks. International shipments can take 3-4 weeks or more, depending on logistics and customs procedures.
Installation (1-4 weeks):
- The installation process can take from 1-4 weeks, depending on the complexity of the installation site, the type of elevator, and any necessary site preparation or modifications. For example, installing a simple residential elevator might take 1-2 weeks, while a more complex installation, such as a custom or large-capacity elevator, can take 3-4 weeks.
Summary
In total, the process from design to installation can take anywhere from 9 to 28 weeks, with standard elevators typically on the shorter end of this range and custom elevators on the longer end. Here is a breakdown:
- Standard Elevators: 9-16 weeks
- Custom Elevators: 16-28 weeks
These timelines are approximate and can vary depending on specific circumstances, such as the manufacturer's schedule, availability of materials, and the complexity of the project.
After we release the unit for production by sending the “approved” elevator shop drawings back to the residential elevatorresidential elevator manufacturer it can take anywhere from 4 to 8 weeks to manufacture. Some special order models can take longer
Full “approval” requires the home owner or contractor/builder and Elevator Project Manager to field verify all the hoist way dimensions and confirm all of the elevator features & selections. All of these selections are documented on the elevator blue prints called “shop drawings”. Then “approval” is signed by the builder, owner & elevator project manager.